The plan for Mini-TAR at NCS1 in 2023 was mutually agreed upon by PV GAS Nam Con Son Pipeline Company (NCSP) and all partners in the pipeline supply chain. It was scheduled to coincide with the outside platform maintenance and the period of the lowest demand in the year. The anticipated turnaround was 2 days, from September 23rd to September 24th.
The O&M on the control room of NCS1 Processing Plant Starting from March 2023, preparations for Mini-TAR 2023 had been underway, encompassing comprehensive planning, optimization of all related activities, personnel mobilization, procurement of materials, approval of relevant documents and procedures, and coordination with relevant units to ensure security and safety during the implementation process. Mini-TAR 2023 consisted of 20 packages with 46 tasks. Engineers and technicians from NCSP, along with experts from the contractor, carried out the inspection of equipment systems, pipelines, and performed repairs to rectify any equipment or technology-related issues arising.


Mini-TAR 2023 still ensured the Safety - Health - Environment goals
Mini-TAR 2023 for NCS1 System was completed ahead of schedule by 1.3 days and almost 8 hours earlier than the optimized plan.